Each stage carries the load of the one above it down into the ground, so we check each part before the next one goes on.
Checking the lot first
Flood exposure varies by address in Marietta. Before we settle on deck elevation or set any post near a drainage corridor, we run your address through the city's property-specific floodplain lookup. If the lot sits in a flood-prone area, that changes how high we build and where the posts can go, and we would rather know before the first hole is dug.
The service behind this guide: composite deck builder. Need a deck builder in Marietta? Our main page lists everything.
Step by step through the job
We excavate and form the footings, then have footing depth and bearing verified before any concrete is poured. Soil here moves with the wet and dry seasons, so we don't pour until that check is done.
Next come the posts and beams, which set the primary load path for everything above them. Joists follow, then the decking, fastened down with deck screws. At final inspection the guardrail height, baluster spacing, stair risers and tread dimensions are all verified.
Work can't move past the footing check or the final inspection until each one is signed off, so inspection timing sets a good part of our schedule, along with the deck's size and the weather.

Where the money goes
Decking material runs $2,900 to $4,300. Framing materials (joists, beams, posts and hardware) run $1,600 to $2,700. Each one gets its own line on our written quote.
Getting a price
On the first phone call we'll talk through a typical range for a deck your size. After we've walked the lot, run the floodplain lookup and measured the space, the exact figure goes in writing along with a stage-by-stage schedule.